117824PRICES SUBJECT TO REVIEW27/08/2024 10:15:15 AM

[EventId:202408271020_review] Prices for interval 27-Aug-2024 10:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1015 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117823PRICES SUBJECT TO REVIEW27/08/2024 10:10:20 AM

[EventId:202408271015_review] Prices for interval 27-Aug-2024 10:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1010 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117822PRICES SUBJECT TO REVIEW27/08/2024 10:05:26 AM

[EventId:202408271010_review] Prices for interval 27-Aug-2024 10:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1005 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117821PRICES SUBJECT TO REVIEW27/08/2024 10:00:18 AM

[EventId:202408271005_review] Prices for interval 27-Aug-2024 10:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1000 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117820PRICES SUBJECT TO REVIEW27/08/2024 09:55:25 AM

[EventId:202408271000_review] Prices for interval 27-Aug-2024 10:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0955 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 10:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117819PRICES SUBJECT TO REVIEW27/08/2024 09:50:20 AM

[EventId:202408270955_review] Prices for interval 27-Aug-2024 09:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0950 hrs on 27 August 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Aug-2024 09:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117783POWER SYSTEM EVENTS25/08/2024 10:33:54 AM

Update - Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 25/08/2024

Refer AEMO Electricity Market Notice 117782

At 1023 hrs the New Norfolk A 110kV Bus was returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
117782POWER SYSTEM EVENTS25/08/2024 09:24:53 AM

Non-credible contingency event - TAS region - 25/08/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 25/08/2024

At 0850 hrs the New Norfolk A 110kV Bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
117690SETTLEMENTS RESIDUE15/08/2024 07:30:20 PM

[EventId:202408151930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 15 August 2024 19:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1930 hrs on 15 August 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 15 August 2024.

Refer to market notice: 117686

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 15 August 2024.

This is an AEMO autogenerated Market Notice.