Market Notices

117382SETTLEMENTS RESIDUE20/07/2024 01:30:31 PM

[EventId:202407201330_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 20 July 2024 13:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1330 hrs on 20 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1330 hrs on 20 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117324LOAD RESTORE08/07/2024 09:58:40 PM

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

Refer to AEMO Electricity Market Notice 117322
Load restoration as directed is complete. Direction cancelled from 2200 hrs 08/07/2024

Manager NEM Real Time Operations
117322LOAD RESTORE08/07/2024 07:34:37 PM

Load Restoration Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Restoration Direction in the NSW Region

AEMO has directed load restoration commencing at 1930 hrs 08/07/2024
in the NSW region

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
117285SETTLEMENTS RESIDUE03/07/2024 05:55:22 PM

[EventId:202407031755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 July 2024 17:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 3 July 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Refer to market notice: 117283

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 3 July 2024.

This is an AEMO autogenerated Market Notice.
117283SETTLEMENTS RESIDUE03/07/2024 05:30:25 PM

[EventId:202407031730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 July 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 July 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 3 July 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
117230PRICES SUBJECT TO REVIEW27/06/2024 05:55:10 PM

[EventId:202406271800_review] Prices for interval 27-Jun-2024 18:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1755 hrs on 27 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 18:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117229PRICES SUBJECT TO REVIEW27/06/2024 05:50:19 PM

[EventId:202406271755_review] Prices for interval 27-Jun-2024 17:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1750 hrs on 27 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117228PRICES SUBJECT TO REVIEW27/06/2024 05:45:13 PM

[EventId:202406271750_review] Prices for interval 27-Jun-2024 17:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1745 hrs on 27 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
117227PRICES SUBJECT TO REVIEW27/06/2024 05:40:15 PM

[EventId:202406271745_review] Prices for interval 27-Jun-2024 17:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1740 hrs on 27 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 27-Jun-2024 17:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm