[EventId:202412161730_confirmed] Prices for interval 16-Dec-2024 17:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:30.
In accordance with Market Notice 122031 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161720_confirmed] Prices for interval 16-Dec-2024 17:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1745 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:20.
In accordance with Market Notice 122028 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161715_confirmed] Prices for interval 16-Dec-2024 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:15.
In accordance with Market Notice 122027 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161710_confirmed] Prices for interval 16-Dec-2024 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:10.
In accordance with Market Notice 122026 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412161705_confirmed] Prices for interval 16-Dec-2024 17:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 December 2024
PRICES ARE NOW CONFIRMED for trading interval 16-Dec-2024 17:05.
In accordance with Market Notice 122024 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/12/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs
The capacity reserve requirement is 1340 MW
The minimum capacity reserve available is 1297 MW
Manager NEM Real Time Operations
[EventId:202412161700_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 December 2024 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 16 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 December 2024.
Refer to market notice: 122016
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1700 hrs on 16 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412161530_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 16 December 2024 15:30
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 16 December 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 December 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1530 hrs on 16 December 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 122002 is cancelled at 1330 hrs 16/12/2024.
Manager NEM Real Time Operations