Filter by category
Filter by Date
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117548 has been updated at 1815 hrs to the following:
[1.] From 1930 hrs 05/08/2024 to 2130 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 386 MW.
Manager NEM Real Time Operations
[EventId:202408051640_confirmed] Prices for interval 05-Aug-2024 16:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:40.
In accordance with Market Notice 117549 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051700_confirmed] Prices for interval 05-Aug-2024 17:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 17:00.
In accordance with Market Notice 117553 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051655_confirmed] Prices for interval 05-Aug-2024 16:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:55.
In accordance with Market Notice 117552 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051650_confirmed] Prices for interval 05-Aug-2024 16:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:50.
In accordance with Market Notice 117551 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051645_confirmed] Prices for interval 05-Aug-2024 16:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:45.
In accordance with Market Notice 117550 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408051635_confirmed] Prices for interval 05-Aug-2024 16:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 5 August 2024
PRICES ARE NOW CONFIRMED for trading interval 05-Aug-2024 16:35.
In accordance with Market Notice 117548 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 05/08/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1900 hrs 05/08/2024 to 2200 hrs 05/08/2024.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 317 MW.
Manager NEM Real Time Operations
Increase to QNI limit to next hold point of 1400 MW Qld to NSW
Refer to market notices 117060.
AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.
The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations