Market Notices

117734RECLASSIFY CONTINGENCY20/08/2024 05:51:22 PM

Reclassification of a Non Credible Contingency Event: Trip of Golden Plains No. 1 220 kV bus - Vic region - 20/08/2024

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non Credible Contingency Event: Trip of Golden Plains No. 1 220 kV bus - Vic region - 20/08/2024

Based on advice from the TNSP, AEMO has reclassified the trip of Golden Plains No. 1 220 kV bus as a credible contingency event.

Constraint Set invoked: NIL

Duration: 20/08/2024 1750 hrs until further notice

Manager NEM Real Time Operations
117727RECLASSIFY CONTINGENCY20/08/2024 03:06:02 PM

Cancellation - Special Reclassification of Transmission Equipment during lightning: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers - Qld region

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a Non-Credible contingency event as a Credible contingency event.

AEMO no longer considers the H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers to be vulnerable due to lightning. Accordingly, its classification has reverted to a non-credible contingency event.

Region: Qld

Transmission Equipment: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers.

Constraint(s): NIL
Cancellation time: 1500 hrs

Refer AEMO Electricity Market Notice 112974

Manager NEM Real Time Operations
117689RECLASSIFY CONTINGENCY15/08/2024 07:14:36 PM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 15/08/2024 19:14

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 117683

Auto-generated on behalf of Manager NEM Real Time Operations
117683RECLASSIFY CONTINGENCY15/08/2024 05:11:11 PM

Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Duration: 15/08/2024 17:11 until further notice

Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
117671RECLASSIFY CONTINGENCY14/08/2024 08:45:51 AM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition - NEM region.

AEMO ELECTRICITY MARKET NOTICE.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 117660 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 0845hrs 14/08/2024.

No constraints were invoked during this event

Manager NEM Real Time Operations
117660RECLASSIFY CONTINGENCY12/08/2024 10:40:27 PM

Reclassification of non-credible contingency event due to existence of widespread abnormal condition/s - NEM regions

AEMO ELECTRICITY MARKET NOTICE.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely Severe Space Weather Watch in the NEM regions.

AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

Duration: 2230 hrs 12/08/2024 until further notice

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).

Manager NEM Real Time Operations
117658RECLASSIFY CONTINGENCY12/08/2024 07:20:23 PM

Cancellation of the reclassification of a Non-Credible contingency event: Buronga - Balranald X3 220 kV line, Buronga - Red Cliffs 0X1 220 kV kV line and Buronga - Broken Hill X2 220 kV line in NSW

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a Non-Credible contingency event as a Credible contingency event. AEMO considers the simultaneous trip of the following elements is no longer reasonably possible. Accordingly, its classification has reverted to a non-credible contingency event.

Region: NSW

Elements: Liddell - Buronga - Balranald X3 220 kV line, Buronga - Red Cliffs 0X1 220 kV kV line and Buronga - Broken Hill X2 220 kV line.

Cancellation time: 1915 hrs

Refer AEMO Electricity Market Notice 117595

Manager NEM Real Time Operations
117654RECLASSIFY CONTINGENCY12/08/2024 02:34:10 PM

Cancellation of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Cancellation time: 12/08/2024 14:34

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 117653

Auto-generated on behalf of Manager NEM Real Time Operations
117653RECLASSIFY CONTINGENCY12/08/2024 01:30:56 PM

Reclassification of a Non-Credible Contingency Event: Collinsville North - Proserpine No.7125 132 kV line and Collinsville North - Proserpine No.7126 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville North - Proserpine No.7125 132 kV and Collinsville North - Proserpine No.7126 132 kV

Duration: 12/08/2024 13:30 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm