Inter-regional transfer limit variation - Tarrone K1 500/132 kV Transformer - VIC region - 06/06/2024
Inter-regional transfer limit variation - Tarrone K1 500/132 kV Transformer - VIC region - 06/06/2024
At 1058 hrs 06/06/2024 there was an unplanned outage of Tarrone K1 500/132 kV Transformer.
The following constraint set(s) invoked at 1115 hrs 06/06/2024
V-TRTS_BUS_CB_500
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)
AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.
Constraint set I-CTRL_ISSUE_TE invoked from 0805 hrs.
The constraint set contains equations with the following interconnector on the LHS:
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details
Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 05/06/2024
Network Augmentation Commissioned - QLD Region - 05/06/2024
H20 Broadsound 275 kV Bus Reactor 1 (150 MVAr) has been commissioned as at 1043 hrs.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 2135 hrs 04/06/2024
N-MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 1 Leg of Directlink .
The following constraint set was invoked at 1945 hrs 04/06/2024
N-MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202406041900_review] Prices for interval 04-Jun-2024 19:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1855 hrs on 4 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 19:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406041855_review] Prices for interval 04-Jun-2024 18:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1850 hrs on 4 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406041850_review] Prices for interval 04-Jun-2024 18:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1845 hrs on 4 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406041845_review] Prices for interval 04-Jun-2024 18:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1840 hrs on 4 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.