Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117126
The synchronous generating units currently expected to be synchronised in SA from 2300 hrs 25/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 25/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024
Inter-regional transfer limit variation - Hazelwood - South Morang No 1 500 kV Line - VIC region - 25/06/2024
A planned outage of Hazelwood - South Morang No 1 500 kV Line in the VIC region was scheduled from 0800 hrs 25/06/2024 to 1530 hrs 25/06/2024.
The outage has been completed and Hazelwood - South Morang No 1 500 kV Line returned to service at 1016 hrs 25/06/2024
Constraint set(s) revoked: V-HWSM
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 2300 hrs 25/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 23/06/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 23/06/2024
Refer Market Notice 117109
The AEMO Intervention Event and all associated directions are cancelled from 1455 hrs 24/06/2024
Manager NEM Real Time Operations
Direction - SA region 24/06/2024
Direction - SA region 24/06/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1505 hrs on 24/06/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117114
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 25/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1500 hrs 24/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 25/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Direction - SA region 23/06/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1640 hrs on 23/06/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117101
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 24/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1630 hrs 23/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations