Cancellation: Reclassification of a Non-Credible Contingency Event: Biloela -Biloela Tee 7110/2 132kV line and Biloela -Biloela Tee 7109/2 132kV line in QLD due to Other Threats.
AEMO considers the occurrence of a non-credible contingency event due to other threats advised in AEMO Electricity Market Notice 118563 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1930 hrs 02/10/2024.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Biloela -Biloela Tee 7110/2 132kV line and Biloela -Biloela Tee 7109/2 132kV line in QLD due to Other Threats.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Other Threats. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD
Lines: Biloela -Biloela Tee 7110/2 132kV line and Biloela -Biloela Tee 7109/2 132kV line
Duration:15:00 hrs 02/10/2024 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 118548 has been updated at 1400 hrs 02/10/2024 to the following:
1. From 1730 hrs to 1930 hrs 08/10/2024.
The forecast capacity reserve requirement is 1107 MW.
The minimum capacity reserve available is 797 MW.
2. From 2100 hrs to 2130 hrs 08/10/2024.
The forecast capacity reserve requirement is 1118 MW.
The minimum capacity reserve available is 972 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/10/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
1. From 1730 hrs to 2030 hrs 08/10/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 668 MW.
2. From 2100 hrs to 2200 hrs 08/10/2024.
The forecast capacity reserve requirement is 1120 MW.
The minimum capacity reserve available is 816 MW.
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Cancellation time: 30/09/2024 03:43
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 118526
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 30/09/2024 01:41 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 27/09/2024 17:53
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 118485
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 27/09/2024 17:53
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 118484
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Duration: 27/09/2024 15:49 until further notice
Constraint set(s) invoked:
NONE