CHG0090631 | Production | Planned Maintenance to Norwest Internet firewall.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet firewall.
Change Start Date & Time: 18/06/2024 20:00:49 AEST
Change End Date & Time: 18/06/2024 23:30:49 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Nil
B2B VPN - May experience a short 5-10 second drop of VPN tunnel connectivity to Norwest DC.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point prior to this scheduled outage.
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0090782 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 26/06/2024 09:00:00 AEST
Change End Date & Time: 26/06/2024 22:00:00 AEST
Outage Start Date & Time: 26/06/2024 18:30:00 AEST
Outage End Date & Time: 26/06/2024 21:00:00 AEST
Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/06/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 117049 is cancelled at 1600 hrs 18/06/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 21/06/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 117041 is cancelled at 1500 hrs 18/06/2024.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/06/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.117045 is cancelled at 1600 hrs 18/06/2024.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024
Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024
A planned outage of Collector Wind Farm to Yass 3L 330kV line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 08/07/2024.
The outage has been completed and Collector Wind Farm to Yass 3L 330kV line returned to service at 1515 hrs 18/06/2024
Constraint set revoked: N-CTYS_3L_WG_CLOSE
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/06/2024
The Forecast LOR2 condition in the NSW region for 20/06/2024 advised in AEMO Electricity Market Notice No. 117040 has been updated at 1500 hrs 18/06/2024 to the following:
From 1700 hrs to 2100 hrs 20/06/2024.
The forecast capacity reserve requirement is 1246 MW.
The minimum capacity reserve available is 1152 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
CHG0090106 | Cancelled | Production | Identity Service Site Transfer
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Identity Service (IDS)
Change Title: Identity Service Site Transfer
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/06/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 19/06/2024 to 1930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1052 MW.
The minimum capacity reserve available is 851 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.