116975RESERVE NOTICE13/06/2024 03:43:12 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

1. From 0630 hrs to 1100 hrs 15/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1606 MW.

2. From 1330 hrs to 2359 hrs 15/06/2024.
The forecast capacity reserve requirement is 1780 MW.
The minimum capacity reserve available is 1523 MW.

AEMO Operations
116974RESERVE NOTICE13/06/2024 03:42:06 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 116973 is cancelled at 1400 hrs 13/06/2024.

AEMO Operations
116973RESERVE NOTICE12/06/2024 03:36:19 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1730 hrs to 2100 hrs 19/06/2024.
The forecast capacity reserve requirement is 437 MW.
The minimum capacity reserve available is 436 MW.

AEMO Operations
116972RESERVE NOTICE12/06/2024 03:34:44 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 0000 hrs to 0030 hrs 20/06/2024.
The forecast capacity reserve requirement is 1830 MW.
The minimum capacity reserve available is 1651 MW.

AEMO Operations
116971RESERVE NOTICE12/06/2024 03:28:20 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116943 has been updated at 1400 hrs 12/06/2024 to the following:

1. From 0600 hrs to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1731 MW.
The minimum capacity reserve available is 1497 MW.

2. From 1630 hrs to 2359 hrs 19/06/2024.
The forecast capacity reserve requirement is 1830 MW.
The minimum capacity reserve available is 1561 MW.

AEMO Operations
116970RESERVE NOTICE12/06/2024 03:27:14 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116942 is cancelled at 1400 hrs 12/06/2024.

AEMO Operations
116969RESERVE NOTICE12/06/2024 03:26:08 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116926 is cancelled at 1400 hrs 12/06/2024.

AEMO Operations
116968MARKET SYSTEMS12/06/2024 09:22:54 AM

CHG0089854: Short Term Trading Market

Change Number: CHG0089854
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
116962PRICES UNCHANGED11/06/2024 06:20:44 PM

[EventId:202406111815_confirmed] Prices for interval 11-Jun-2024 18:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024

PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 18:15.

In accordance with Market Notice 116956 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.