Direction - to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Direction - to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119198
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 24/10/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 25/10/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1630 hrs 25/10/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119237
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 25/10/2024.
The direction update is issued at 1600 hrs 24/10/2024.
Manager NEM Real Time Operations
[EventId:202410241445_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 October 2024 14:45
Issued by Australian Energy Market Operator Ltd at 1445 hrs on 24 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1445 hrs on 24 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202410241430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 24 October 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 24 October 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 October 2024.
Refer to market notice: 119305
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 24 October 2024.
This is an AEMO autogenerated Market Notice.
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 119265
Direction is cancelled from: 1830 hrs 24/10/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - VIC region 24/10/2024
Cancellation - AEMO Intervention Event - VIC region 24/10/2024
Refer to Market Notice 119272
The AEMO Intervention Event and all associated directions are cancelled from 1535 hrs on 24/10/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-3 MURRAY2
Refer to Market Notice 119293
Direction is cancelled from: 1535 hrs 24/10/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2
Cancellation: Direction issued to: Snowy Hydro Limited - MURR2-2 MURRAY2
Refer to Market Notice 119292
Direction is cancelled from: 1535 hrs 24/10/2024
Manager NEM Real Time Operations
[EventId:202410241310_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 24 October 2024 13:10
Issued by Australian Energy Market Operator Ltd at 1310 hrs on 24 October 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 24 October 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1310 hrs on 24 October 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.