Filter by category
Filter by Date
[EventId:202406111805_confirmed] Prices for interval 11-Jun-2024 18:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 18:05.
In accordance with Market Notice 116953 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111800_confirmed] Prices for interval 11-Jun-2024 18:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 18:00.
In accordance with Market Notice 116952 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111755_confirmed] Prices for interval 11-Jun-2024 17:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 17:55.
In accordance with Market Notice 116951 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111750_confirmed] Prices for interval 11-Jun-2024 17:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 11 June 2024
PRICES ARE NOW CONFIRMED for trading interval 11-Jun-2024 17:50.
In accordance with Market Notice 116950 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202406111805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 11 June 2024 18:05
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 11 June 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 11 June 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 11 June 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024
NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/06/2024 12:45 to 11/06/2024 14:25
Amount: -23 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 11 June 2024
NON-CONFORMANCE QLD1 Region Tuesday, 11 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 11/06/2024 11:15 to 11/06/2024 12:05
Amount: -21 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0089972 | Completed | Production | Planned Maintenance to Norwest Internet firewall.
Notification issued to: Market Notice Notification
Type: Completed
Change Type: Normal Service/Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet firewall.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region QLD1 Monday, 10 June 2024
NON-CONFORMANCE QLD1 Region Monday, 10 June 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 10/06/2024 23:35 to 10/06/2024 23:40
Amount: 34 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations