Reclassification of a Non Credible Contingency Event: Trip of Golden Plains No. 1 220 kV bus - Vic region - 20/08/2024
Reclassification of a Non Credible Contingency Event: Trip of Golden Plains No. 1 220 kV bus - Vic region - 20/08/2024
Based on advice from the TNSP, AEMO has reclassified the trip of Golden Plains No. 1 220 kV bus as a credible contingency event.
Constraint Set invoked: NIL
Duration: 20/08/2024 1750 hrs until further notice
Manager NEM Real Time Operations
CHG0095840 | Production | AEMO will be undertaking maintenance activities on the DWGM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Change Start Date & Time: 20/08/2024 18:30:35 AEST
Change End Date & Time: 21/08/2024 01:30:35 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements:
AEMO will be undertaking maintenance activities on the DWGM system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
Cancellation - Special Reclassification of Transmission Equipment during lightning: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers - Qld region
Cancellation of the reclassification of a Non-Credible contingency event as a Credible contingency event.
AEMO no longer considers the H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers to be vulnerable due to lightning. Accordingly, its classification has reverted to a non-credible contingency event.
Region: Qld
Transmission Equipment: H14 Middle Ridge No. 2 and No. 3 275/110 kV transformers.
Constraint(s): NIL
Cancellation time: 1500 hrs
Refer AEMO Electricity Market Notice 112974
Manager NEM Real Time Operations
CHG0091298 | Completed | Production | Change to MarketNet SSL VPN
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Market Network
Change Title: Change to MarketNet SSL VPN
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0093465 | Production | AEMO will be undertaking maintenance activities on the STTM system.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the STTM system.
Change Start Date & Time: 20/08/2024 18:31:12 AEST
Change End Date & Time: 21/08/2024 08:31:12 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the STTM system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
CHG0095739 | Production | AEMO will be undertaking maintenance activities on the system.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the system.
Change Start Date & Time: 20/08/2024 13:00:19 AEST
Change End Date & Time: 20/08/2024 16:00:19 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?d=pp_services_status for any planned/unplanned maintenance activities .
CHG0087952 | Completed | Pre-Production | Retail Pre-Production Data refresh (CATS and EMDM)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Retail Pre-Production Data refresh (CATS and EMDM)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0095132 | Cancelled | Production | AEMO will be undertaking maintenance activities on the DWGM system
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the DWGM system
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
CHG0091534 | Completed | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.