Market Notices

117251RECLASSIFY CONTINGENCY30/06/2024 06:19:38 AM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 30/06/2024 06:19

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 117250

Auto-generated on behalf of Manager NEM Real Time Operations
117250RECLASSIFY CONTINGENCY30/06/2024 05:14:55 AM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 30/06/2024 05:14 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
117236PRICES UNCHANGED27/06/2024 06:06:30 PM

[EventId:202406271740_confirmed] Prices for interval 27-Jun-2024 17:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 June 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Jun-2024 17:40.

In accordance with Market Notice 117226 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117235PRICES UNCHANGED27/06/2024 06:05:25 PM

[EventId:202406271800_confirmed] Prices for interval 27-Jun-2024 18:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 June 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Jun-2024 18:00.

In accordance with Market Notice 117230 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117234PRICES UNCHANGED27/06/2024 06:04:13 PM

[EventId:202406271755_confirmed] Prices for interval 27-Jun-2024 17:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 June 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Jun-2024 17:55.

In accordance with Market Notice 117229 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117233PRICES UNCHANGED27/06/2024 06:03:05 PM

[EventId:202406271750_confirmed] Prices for interval 27-Jun-2024 17:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 June 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Jun-2024 17:50.

In accordance with Market Notice 117228 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117232PRICES UNCHANGED27/06/2024 06:01:48 PM

[EventId:202406271745_confirmed] Prices for interval 27-Jun-2024 17:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 June 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Jun-2024 17:45.

In accordance with Market Notice 117227 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117231PRICES UNCHANGED27/06/2024 06:00:15 PM

[EventId:202406271735_confirmed] Prices for interval 27-Jun-2024 17:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1800 hrs on 27 June 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Jun-2024 17:35.

In accordance with Market Notice 117225 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
117223RECLASSIFY CONTINGENCY27/06/2024 03:54:11 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 27/06/2024 15:54

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 117219

Auto-generated on behalf of Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm