Filter by category
Filter by Date
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 117526
Direction is cancelled from: 1230 hrs 02/08/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 117531
Direction is cancelled from: 0105 hrs 02/08/2024
Manager NEM Real Time Operations
Direction - SA region 02/08/2024
Direction - SA region 02/08/2024
Refer to Market Notice 117521
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 0030 hrs 02/08/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0035 hrs 02/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0135 hrs 02/08/2024 / further notice.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 1 August 2024
NON-CONFORMANCE SA1 Region Thursday, 1 August 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 01/08/2024 13:55 to 01/08/2024 17:35
Amount: 28 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
Direction - SA region 01/08/2024
Direction - SA region 01/08/2024
Refer to Market Notice 117521
In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1700 hrs 01/08/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 2230 hrs 01/08/2024
Services provided: Voltage Control
Circumstances necessitating the direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 02/08/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 01/08/2024
Direction - SA region 01/08/2024
Refer to Market Notice 117521
In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1600 hrs 01/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0000 hrs 02/08/2024
Services provided: Voltage Control
Circumstances necessitating the direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1230 hrs 02/08/2024 / further notice.
Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 01/08/2024
Direction - SA region 01/08/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 01/08/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 31/07/2024
Cancellation - AEMO Intervention Event - SA region 31/07/2024
Refer to Market Notice 117515
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 01/08/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 117516
Direction is cancelled from: 1430 hrs 01/08/2024
Manager NEM Real Time Operations