Market Notices

118722RECLASSIFY CONTINGENCY09/10/2024 02:40:55 PM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 09/10/2024 14:40 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
118714PRICES UNCHANGED09/10/2024 01:04:05 PM

[EventId:202410091240_confirmed] Prices for interval 09-Oct-2024 12:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 9 October 2024

PRICES ARE NOW CONFIRMED for trading interval 09-Oct-2024 12:40.

In accordance with Market Notice 118703 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
118713PRICES UNCHANGED09/10/2024 01:06:28 PM

[EventId:202410091300_confirmed] Prices for interval 09-Oct-2024 13:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 9 October 2024

PRICES ARE NOW CONFIRMED for trading interval 09-Oct-2024 13:00.

In accordance with Market Notice 118708 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
118712PRICES UNCHANGED09/10/2024 01:03:01 PM

[EventId:202410091255_confirmed] Prices for interval 09-Oct-2024 12:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 9 October 2024

PRICES ARE NOW CONFIRMED for trading interval 09-Oct-2024 12:55.

In accordance with Market Notice 118707 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
118711PRICES UNCHANGED09/10/2024 01:01:56 PM

[EventId:202410091250_confirmed] Prices for interval 09-Oct-2024 12:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 9 October 2024

PRICES ARE NOW CONFIRMED for trading interval 09-Oct-2024 12:50.

In accordance with Market Notice 118706 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
118710PRICES UNCHANGED09/10/2024 01:00:25 PM

[EventId:202410091245_confirmed] Prices for interval 09-Oct-2024 12:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 9 October 2024

PRICES ARE NOW CONFIRMED for trading interval 09-Oct-2024 12:45.

In accordance with Market Notice 118704 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
118709PRICES UNCHANGED09/10/2024 01:05:12 PM

[EventId:202410091235_confirmed] Prices for interval 09-Oct-2024 12:35 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1300 hrs on 9 October 2024

PRICES ARE NOW CONFIRMED for trading interval 09-Oct-2024 12:35.

In accordance with Market Notice 118701 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
118692RECLASSIFY CONTINGENCY09/10/2024 06:48:56 AM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 09/10/2024 06:48 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
118690PRICES UNCHANGED08/10/2024 04:16:42 PM

[EventId:202410081550_confirmed] Prices for interval 08-Oct-2024 15:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 8 October 2024

PRICES ARE NOW CONFIRMED for trading interval 08-Oct-2024 15:50.

In accordance with Market Notice 118680 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.