Inter-regional transfer limit variation - [outage element] - NSW region - 04/07/2024
Inter-regional transfer limit variation - Lismore - Dunoon 9U7 132 kV line - NSW region - 04/07/2024
A planned outage of Lismore - Dunoon 9U7 132 kV line in the NSW region was scheduled from 0732 hrs 02/07/2024 to 1700 hrs 19/07/2024.
The outage has been completed and Lismore - Dunoon 9U7 132 kV line returned to service at 1105 hrs 04/07/2024
Constraint set(s) revoked: N-LSDU_9U6
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in SA region 05/07/2024
Cancellation - Possible intervention to manage power system security in SA region 05/07/2024
Refer Market Notice 117281
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 0845 hrs 04/07/2024.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
Cancellation of Actual (LOR1) condition in the NSW region - 03/07/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117284 is cancelled at 2010 hrs 03/07/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 03/07/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 766 MW
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117278
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 05/07/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1300 hrs 04/07/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0000 hrs 05/07/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/06/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 27/06/2024
Refer Market Notice 117221
The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs 29/06/2024
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dumaresq No. 1 330kV SVC - NSW region - 28/06/2024
Inter-regional transfer limit variation - Dumaresq No. 1 330kV SVC- NSW region - 28/06/2024
At 1649 hrs 28/06/2024 there was a short notice outage of the Dumaresq No. 1 330kV SVC.
The following constraint set invoked at 1650 hrs 28/06/2024
N-DM_SVC
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update - Direction - SA Region - 27/06/2024
Update - Direction - SA Region - 27/06/2024
Refer Market Notice 117221
The AEMO intervention event that commenced from interval ending 1605 hrs on 27/06/2024 is continuing.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations