125548POWER SYSTEM EVENTS12/03/2025 09:46:32 AM

Non-credible contingency event - TAS region - 12/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 12/03/2025

At 0909 hrs the Burnie -Smithton Tee Port Latta No. 1 110kV Line and the Burnie -Smithton Tee Port Latta No. 2 110kV Line tripped and auto-reclosed.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
125521NON-CONFORMANCE11/03/2025 11:55:21 AM

NON-CONFORMANCE Region NSW1 Tuesday, 11 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 11 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 11/03/2025 11:25 to 11/03/2025 11:55
Amount: -9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125517POWER SYSTEM EVENTS11/03/2025 10:05:23 AM

Non-credible contingency event - SA region - 11/03/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 11/03/2025

At 0917 hrs the Penola West - South East 132 kV line and the Kincraig - Penola West 132 kV line tripped.

AEMO did not instruct load shedding.

Approximately 3 MW of electrical load has been disconnected.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
125474NON-CONFORMANCE10/03/2025 01:05:17 PM

NON-CONFORMANCE Region QLD1 Monday, 10 March 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 10 March 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 10/03/2025 13:00 to 10/03/2025 13:05
Amount: -11 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
125452RESERVE NOTICE09/03/2025 08:16:22 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125446 is cancelled at 2015 hrs 09/03/2025.

Manager NEM Real Time Operations
     
125446RESERVE NOTICE09/03/2025 07:11:28 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 1930 hrs 09/03/2025 to 2030 hrs 09/03/2025.
The forecast capacity reserve requirement is 650 MW.
The minimum capacity reserve available is 600 MW.


Manager NEM Real Time Operations
     
125431MARKET INTERVENTION09/03/2025 01:27:46 PM

Cancellation - AEMO Intervention Event - SA region 08/03/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 08/03/2025

Refer to Market Notice 125396

The AEMO Intervention Event and all associated directions are cancelled from 1330 hrs on 09/03/2025.


Manager NEM Real Time Operations
     
125426MARKET INTERVENTION09/03/2025 01:25:15 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 125398

Direction is cancelled from: 1330 hrs 09/03/2025

Manager NEM Real Time Operations
     
125425RESERVE NOTICE09/03/2025 11:56:43 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 09/03/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 125424 is cancelled at 1200 hrs 09/03/2025.

Manager NEM Real Time Operations
     