Filter by category
Filter by Date
[EventId:202412251720_confirmed] Prices for interval 25-Dec-2024 17:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:20.
In accordance with Market Notice 122478 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251715_confirmed] Prices for interval 25-Dec-2024 17:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:15.
In accordance with Market Notice 122477 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202412251710_confirmed] Prices for interval 25-Dec-2024 17:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 25 December 2024
PRICES ARE NOW CONFIRMED for trading interval 25-Dec-2024 17:10.
In accordance with Market Notice 122476 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Cancellation time: 25/12/2024 16:44
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122471
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Cancellation time: 25/12/2024 16:09
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122467
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Duration: 25/12/2024 15:40 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Duration: 25/12/2024 15:06 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
Forecast Minimum System Load MSL1 condition in the VIC Region on 01/01/2025
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 01/01/2025.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1660 MW
- MSL2 - 1160 MW
- MSL3 - 660 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
- From 1030 hrs 01/01/2025 to 1430 hrs 01/01/2025. Minimum regional demand is forecast to be 1422 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tumoulin - Woree No.877 275 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tumoulin - Woree No.877 275 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 24/12/2024 22:03
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 122455
Auto-generated on behalf of Manager NEM Real Time Operations