123896PRICES SUBJECT TO REVIEW29/01/2025 04:39:51 PM

[EventId:202501291630_review] Prices for interval 29-Jan-2025 16:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1625 hrs on 29 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jan-2025 16:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123895PRICES SUBJECT TO REVIEW29/01/2025 04:27:09 PM

[EventId:202501291625_review] Prices for interval 29-Jan-2025 16:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1620 hrs on 29 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jan-2025 16:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123894PRICES SUBJECT TO REVIEW29/01/2025 04:20:57 PM

[EventId:202501291620_review] Prices for interval 29-Jan-2025 16:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1615 hrs on 29 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jan-2025 16:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123893PRICES SUBJECT TO REVIEW29/01/2025 04:33:19 PM

[EventId:202501291615_review] Prices for interval 29-Jan-2025 16:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1610 hrs on 29 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jan-2025 16:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123891PRICES SUBJECT TO REVIEW29/01/2025 04:14:49 PM

[EventId:202501291610_review] Prices for interval 29-Jan-2025 16:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1605 hrs on 29 January 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 29-Jan-2025 16:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
123889RECLASSIFY CONTINGENCY29/01/2025 03:56:07 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 29/01/2025 15:56 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
123888RECLASSIFY CONTINGENCY29/01/2025 02:33:56 PM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 29/01/2025 14:33

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 123882

Auto-generated on behalf of Manager NEM Real Time Operations
     
123887RECLASSIFY CONTINGENCY29/01/2025 02:33:56 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 29/01/2025 14:33

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 123883

Auto-generated on behalf of Manager NEM Real Time Operations
     
123886RESERVE NOTICE29/01/2025 02:46:45 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 03/02/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 123813 is cancelled at 1400 hrs 29/01/2025.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm