Filter by category
Filter by Date
[EventId:202501221405_confirmed] Prices for interval 22-Jan-2025 14:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2025 14:05.
In accordance with Market Notice 123564 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501221400_confirmed] Prices for interval 22-Jan-2025 14:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2025 14:00.
In accordance with Market Notice 123562 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501221355_confirmed] Prices for interval 22-Jan-2025 13:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2025 13:55.
In accordance with Market Notice 123561 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501221350_confirmed] Prices for interval 22-Jan-2025 13:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2025 13:50.
In accordance with Market Notice 123559 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501221340_confirmed] Prices for interval 22-Jan-2025 13:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2025 13:40.
In accordance with Market Notice 123557 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 123546 is cancelled at 0800 hrs 22/01/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 28/01/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1630 hrs 28/01/2025 to 1700 hrs 28/01/2025.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 570 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Guybal Munjan - Chalumbin 857 275kV line line and Guybal Munjan - Chalumbin 858 275kV line line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Guybal Munjan - Chalumbin 857 275kV line and Guybal Munjan - Chalumbin 858 275kV line
Cancellation time: 22/01/2025 06:04
Constraint set(s) revoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 123542
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Chalumbin - Turkinje No.7165 132 kV line and Chalumbin - Turkinje No.7166 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Chalumbin - Turkinje No.7165 132 kV and Chalumbin - Turkinje No.7166 132 kV
Cancellation time: 22/01/2025 06:04
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 123541
Auto-generated on behalf of Manager NEM Real Time Operations