[EventId:202501221340_confirmed] Prices for interval 22-Jan-2025 13:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 22 January 2025
PRICES ARE NOW CONFIRMED for trading interval 22-Jan-2025 13:40.
In accordance with Market Notice 123557 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202501221355_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 22 January 2025 13:55
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 22 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.
Refer to market notice: 123556
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1355 hrs on 22 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501221345_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 22 January 2025 13:45
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 22 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 22 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1345 hrs on 22 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501221330_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 January 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 22 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1330 hrs on 22 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501221140_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 22 January 2025 11:40
Issued by Australian Energy Market Operator Ltd at 1140 hrs on 22 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.
Refer to market notice: 123553
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1140 hrs on 22 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501221035_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 22 January 2025 10:35
Issued by Australian Energy Market Operator Ltd at 1035 hrs on 22 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 22 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1035 hrs on 22 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501211630_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 January 2025 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 21 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.
Refer to market notice: 123526
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1630 hrs on 21 January 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202501211450_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 21 January 2025 14:50
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 21 January 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1450 hrs on 21 January 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202501211330_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 21 January 2025 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 21 January 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 21 January 2025.
Refer to market notice: 123515
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1330 hrs on 21 January 2025.
This is an AEMO autogenerated Market Notice.