Cancellation - AEMO Intervention Event - SA region 16/12/2024
Cancellation - AEMO Intervention Event - SA region 16/12/2024
Refer to Market Notice 122011
The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 19/12/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122198
Direction is cancelled from: 1530 hrs 19/12/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122199
Direction is cancelled from: 1500 hrs 19/12/2024
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122110
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 19/12/2024.
The direction update is issued at 1600 hrs 18/12/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122111
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 19/12/2024.
The direction update is issued at 1600 hrs 18/12/2024.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 22/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 22/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1760 MW
o MSL2 - 1260 MW
o MSL3 - 760 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1400 hrs 22/12/2024. Minimum regional demand is forecast to be 1622 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 122013
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.
The direction update is issued at 1630 hrs 17/12/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 122012
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 19/12/2024.
The direction update is issued at 1630 hrs 17/12/2024.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 21/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 21/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1705 MW
o MSL2 - 1205 MW
o MSL3 - 705 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
From 1130 hrs to 1330 hrs 21/12/2024. Minimum regional demand is forecast to be 1643 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .