[EventId:202412161735_review] Prices for interval 16-Dec-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161730_review] Prices for interval 16-Dec-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161725_review] Prices for interval 16-Dec-2024 17:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161720_review] Prices for interval 16-Dec-2024 17:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1715 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161715_review] Prices for interval 16-Dec-2024 17:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1710 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161710_review] Prices for interval 16-Dec-2024 17:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1705 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412161700_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 16 December 2024 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 16 December 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 16 December 2024.
Refer to market notice: 122016
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1700 hrs on 16 December 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202412161705_review] Prices for interval 16-Dec-2024 17:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 16 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Dec-2024 17:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV
Duration: 16/12/2024 16:22 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations