Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 117126
The synchronous generating units currently expected to be synchronised in SA from 2300 hrs 25/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 25/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
[EventId:202406251355_review] Prices for interval 25-Jun-2024 13:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1350 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251350_review] Prices for interval 25-Jun-2024 13:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251345_review] Prices for interval 25-Jun-2024 13:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251340_review] Prices for interval 25-Jun-2024 13:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251335_review] Prices for interval 25-Jun-2024 13:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406251330_review] Prices for interval 25-Jun-2024 13:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 25 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 25-Jun-2024 13:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Non-credible contingency event - NSW region - 25/06/2024
Non-credible contingency event - NSW region - 25/06/2024
At 0901 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 2300 hrs 25/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations