Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024
Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024
Based on advice from the asset owner, AEMO has declared the simultaneous trip of Eraring Power Station Units 2 and 4 as a credible contingency event.
AEMO considers the simultaneous trip of those generators to now be more likely.
AEMO has reclassified this as a credible contingency event from 1000 hrs 23/09/2024.
To manage power system security constraint set N-ERARING_N-2 invoked from 1000 hrs 23/09/2024 until further notice.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT
Refer to Market Notice 118386
Direction is cancelled from: 0400 hrs 23/09/2024
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 22/09/2024
Cancellation - AEMO Intervention Event - SA region 22/09/2024
Refer to Market Notice 118376
The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 23/09/2024.
Manager NEM Real Time Operations
Direction - SA region 22/09/2024
Direction - SA region 22/09/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1855 hrs on 22/09/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Direction - SA region 22/09/2024
Direction - SA region 22/09/2024
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1850 hrs 22/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1850 hrs 22/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1950 hrs 22/09/2024.
Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 22/09/2024
Direction - SA region 22/09/2024
Refer to Market Notice 118371
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1530 hrs 22/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 0700 hrs 23/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 24/09/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Direction - SA region 22/09/2024
Direction - SA region 22/09/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1535 hrs on 22/09/2024.
Intervention pricing does not apply to this AEMO intervention event.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
Manager NEM Real Time Operations
Direction - SA region 22/09/2024
Direction - SA region 22/09/2024
Refer to Market Notice 118371
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1530 hrs 22/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 0900 hrs 23/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1530 hrs 23/09/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 118365
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 23/09/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1530 hrs 22/09/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations