Filter by category
Filter by Date
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 2130 hrs 11/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Direction - SA region 09/06/2024
Direction - SA region 09/06/2024
In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).
The direction was necessary to maintain the power system in a secure operating state.
AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.
The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 09/06/2024.
Intervention pricing does not apply to this AEMO intervention event.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA region
Update - Possible intervention to manage power system security in SA region
Refer AEMO Electricity Market Notice 116914
The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 10/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO estimates that, in the absence of sufficient market response by 1600 hrs 09/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 10/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .
Manager NEM Real Time Operations
CHG0090456 | Production | Renewal and update of AEMO's FBS_Prod_Hub.aemo.com.au server certificate.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Renewal and update of AEMO's FBS_Prod_Hub.aemo.com.au server certificate.
Change Start Date & Time: 07/07/2024 10:00:00 AEST
Change End Date & Time: 07/07/2024 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO's FRC Gas Hub web services need to have their server certificates updated every year with new certificates to replace the expiring one.
Participants connecting to these endpoints or receiving requests from AEMO's FRC Gas Hub platforms and have authorisation mechanisms like certificate fingerprinting in place will notice a change in AEMO's server's certificate fingerprint and will need to update their systems accordingly.
The certificate relates to "FBS-Prod-Hub.aemo.com.au" certificate and relates to the following domains.
FBS-Prod-Hub.aemo.com.au
apis.prod.aemo.com.au
hub.aemo.com.au
prod.frchub.net
apis.prod.marketnet.net.au
hub.marketnet.net.au
Participants WILL need to update the profile that communicates with the above domains.
This will need to be done to avoid the inability to send messages to the relay.
The certificates can be downloaded from the link below:
https://www.digicert.com/secure/download-certificate/kb7jy1dywm60d2hnjfxl4bbblmgs2bh
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0089972 | Production | Planned Maintenance to Norwest Internet firewall.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet Access
Change Title: Planned Maintenance to Norwest Internet firewall.
Change Start Date & Time: 09/06/2024 08:00:40 AEST
Change End Date & Time: 09/06/2024 10:00:40 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Nil
B2B VPN - May experience a short 5-10 second drop of VPN tunnel connectivity to Norwest DC.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point prior to this scheduled outage.
SSL VPN Participants: Nil
GASHUB: Nil
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 06/06/2024 13:34
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 116902
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 06/06/2024 12:30 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0089854 | Production | Planned Outage for the Gas Short Term Trading Market Systems Production.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Short Term Trading Market
Change Title: Planned Outage for the Gas Short Term Trading Market Systems Production.
Change Start Date & Time: 11/06/2024 09:00:00 AEST
Change End Date & Time: 11/06/2024 22:00:00 AEST
Outage Start Date & Time: 11/06/2024 18:30:00 AEST
Outage End Date & Time: 11/06/2024 21:00:00 AEST
Environment: Production
Participant Impact and Requirements: Gas Short Term Trading Market (STTM) services including SWEX and MIS, SPI and SBS will not be available during the outage window in Production.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.