Direction - SA region 26/08/2024
Direction - SA region 26/08/2024
Refer to Market Notice 117813
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 28/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1200 hrs 29/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 30/08/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117892
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 30/08/2024.
The direction update is issued at 1548 hrs 28/08/2024.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
Inter-regional transfer limit variation - Dumaresq 330 kV SVC - NSW region - 28/08/2024
At 1125 hrs 28/08/2024 there was a short notice outage of Dumaresq 330 kV SVC.
The following constraint set(s) invoked at 1125 hrs 28/08/2024
N-DM_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117894
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1800 hrs 28/08/2024.
The direction update is issued at 1000 hrs 28/08/2024.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in NSW region - 28/08/2024
In order to maintain the power system in a secure operating state in the NSW region, AEMO has invoked automated constraint set CA_SYDS_55E0E615 from 0900 hrs until further notice.
This constraint set contains equations with the following interconnector on the LHS;
N-Q-MNSP1
Refer to AEMO Network Outage Scheduler (NOS) for further information.
Manager NEM Real Time Operations
[EventId:202408271545_confirmed] Prices for interval 27-Aug-2024 15:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 27 August 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 15:45.
In accordance with Market Notice 117891 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408271605_confirmed] Prices for interval 27-Aug-2024 16:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 27 August 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 16:05.
In accordance with Market Notice 117897 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408271600_confirmed] Prices for interval 27-Aug-2024 16:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 27 August 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 16:00.
In accordance with Market Notice 117896 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408271555_confirmed] Prices for interval 27-Aug-2024 15:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1605 hrs on 27 August 2024
PRICES ARE NOW CONFIRMED for trading interval 27-Aug-2024 15:55.
In accordance with Market Notice 117895 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.