117094RESERVE NOTICE21/06/2024 04:08:04 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 24/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 0700 hrs to 0830 hrs 24/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1705 MW.

2. From 1630 hrs to 1700 hrs 24/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1707 MW.

3. From 1730 hrs to 1930 hrs 24/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1702 MW.

AEMO Operations
117089RECLASSIFY CONTINGENCY21/06/2024 12:39:41 AM

Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Cancellation time: 21/06/2024 00:39

Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Refer AEMO Electricity Market Notice 117088

Auto-generated on behalf of Manager NEM Real Time Operations
117088RECLASSIFY CONTINGENCY20/06/2024 11:34:51 PM

Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV

Duration: 20/06/2024 23:34 until further notice

Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
117085RESERVE NOTICE20/06/2024 05:53:01 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117084 is cancelled at 1745 hrs 20/06/2024.

Manager NEM Real Time Operations
117084RESERVE NOTICE20/06/2024 03:10:54 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117080 has been updated at 1500 hrs to the following:

[1.] From 1730 hrs 20/06/2024 to 1900 hrs 20/06/2024.
The forecast capacity reserve requirement is 1770 MW.
The minimum capacity reserve available is 1682 MW.

Manager NEM Real Time Operations
117083MARKET INTERVENTION20/06/2024 12:55:37 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 19/06/2024

Refer Market Notice 117076

The AEMO Intervention Event and all associated directions are cancelled from 1300 hrs 20/06/2024

Manager NEM Real Time Operations
117080RESERVE NOTICE20/06/2024 12:48:26 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117074 has been updated at 1239 hrs to the following:

[1.] From 1730 hrs 20/06/2024 to 1930 hrs 20/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1349 MW.


Manager NEM Real Time Operations
117079RESERVE NOTICE19/06/2024 06:47:26 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 117073 is cancelled at1845 hrs 19/06/2024

Manager NEM Real Time Operations
117076MARKET INTERVENTION19/06/2024 04:42:31 PM

Direction - SA region 19/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 19/06/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1650 hrs on 19/06/2024.

Intervention pricing does not apply to this AEMO intervention event.