Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Cancellation time: 30/08/2024 05:14
Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Refer AEMO Electricity Market Notice 117978
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV
Duration: 30/08/2024 04:12 until further notice
Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 117976 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 0130 hrs 30/08/2024.
Constraint set revoked: I-VS_250
Manager NEM Real Time Operations
Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - SA region.
AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the SA region.
AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.
AEMO has taken the following action to maintain power system security at 2310 hrs 29/08/2024.
Constraint set invoked: I-VS_250
Duration: 2310 hrs 29/08/2024 until further notice
Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).
Manager NEM Real Time Operations
[EventId:202408291910_confirmed] Prices for interval 29-Aug-2024 19:10 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:10.
In accordance with Market Notice 117962 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408291930_confirmed] Prices for interval 29-Aug-2024 19:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:30.
In accordance with Market Notice 117969 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408291925_confirmed] Prices for interval 29-Aug-2024 19:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:25.
In accordance with Market Notice 117968 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408291920_confirmed] Prices for interval 29-Aug-2024 19:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:20.
In accordance with Market Notice 117965 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202408291915_confirmed] Prices for interval 29-Aug-2024 19:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 29 August 2024
PRICES ARE NOW CONFIRMED for trading interval 29-Aug-2024 19:15.
In accordance with Market Notice 117963 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.