Market Notices

127302MARKET SYSTEMS27/05/2025 10:57:00 AM

Initial - CHG0103591 - Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)

Change Number: CHG0103591

Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Change Start Date & Time: 28/05/2025 13:00:00
Change End Date & Time: 28/05/2025 17:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: no outage, deployment will be made to msats 1a first then switch to msats 1b.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
     
127283SETTLEMENTS RESIDUE26/05/2025 06:45:15 PM

[EventId:202505261845_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 26 May 2025 18:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 26 May 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 May 2025.

Refer to market notice: 127279

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1845 hrs on 26 May 2025.

This is an AEMO autogenerated Market Notice.
     
127279SETTLEMENTS RESIDUE26/05/2025 05:30:25 PM

[EventId:202505261730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 26 May 2025 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 26 May 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 26 May 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 26 May 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127270MARKET SYSTEMS26/05/2025 11:10:07 AM

Completed - CHG0103179 - Scheduled maintenance of Marketnet router in Brisbane

Change Number: CHG0103179

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled maintenance of Marketnet router in Brisbane

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
127251PRICES SUBJECT TO REVIEW25/05/2025 10:20:21 PM

[EventId:202505252225_review] Prices for interval 25-May-2025 22:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2220 hrs on 25 May 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 25-May-2025 22:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127250PRICES SUBJECT TO REVIEW25/05/2025 10:15:16 PM

[EventId:202505252220_review] Prices for interval 25-May-2025 22:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2215 hrs on 25 May 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 25-May-2025 22:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127248PRICES SUBJECT TO REVIEW25/05/2025 10:10:28 PM

[EventId:202505252215_review] Prices for interval 25-May-2025 22:15 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2210 hrs on 25 May 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 25-May-2025 22:15.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127247PRICES SUBJECT TO REVIEW25/05/2025 10:05:22 PM

[EventId:202505252210_review] Prices for interval 25-May-2025 22:10 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2205 hrs on 25 May 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 25-May-2025 22:10.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
127246PRICES SUBJECT TO REVIEW25/05/2025 10:00:26 PM

[EventId:202505252205_review] Prices for interval 25-May-2025 22:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2200 hrs on 25 May 2025

PRICES ARE SUBJECT TO REVIEW for trading interval 25-May-2025 22:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     