Network Augmentation Commissioned - SA Region - 18/12/2024
Network Augmentation Commissioned - SA Region - 18/12/2024
At 0910 hrs 18/12/2024, the Para East Left Bus 275 kV Reactor has been commissioned.
Manager NEM Real Time Operations
[EventId:202412180930_review] Prices for interval 18-Dec-2024 09:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 0925 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412180925_review] Prices for interval 18-Dec-2024 09:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 0920 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412180920_review] Prices for interval 18-Dec-2024 09:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 0915 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412180915_review] Prices for interval 18-Dec-2024 09:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 0910 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412180910_review] Prices for interval 18-Dec-2024 09:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 0905 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202412180905_review] Prices for interval 18-Dec-2024 09:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 0900 hrs on 18 December 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 18-Dec-2024 09:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Project Energy Connect (PEC-1) testing 18th December 2024 0700-2200 for flows in both directions up to 150 MW
Refer to market notice 120706
There is an opportunity for testing Project Energy Connect (PEC-1) for flows in both directions up to 150 MW on 18th December from 07:00hrs to 22:00hrs
This test includes switching of transmission lines and reactive plant in South Australia and in New South Wales.
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 17/12/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 122093 is cancelled at 1140 hrs 17/12/2024.
Manager NEM Real Time Operations