Filter by category
Filter by Date
Possible intervention to manage power system security in SA Region
Possible intervention to manage power system security in SA Region
The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 20/06/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
QNI Minor testing (Qld to NSW) 19th June 2024
Refer to market notice 117027
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Wednesday 19th June 2024 from 0700 to 1000hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Update - Non-credible contingency event - VIC region - 18/06/2024
Update - Non-credible contingency event - VIC region - 18/06/2024
Refer AEMO Electricity Market Notice 117042
The cause of this non credible contingency event is not known at this stage..
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO has therefore reclassified this event as a credible contingency event until further notice.
Region: VIC
Elements: Glenrowan No1 66kV Bus
Duration: 0903 hrs 18/06/2024 until further notice
Constraint set(s) invoked: Nil
Manager NEM Real Time Operations
QNI Minor testing (Qld to NSW) 17th June 2024
Refer to market notice 114742
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1300 MW on Monday 17th June 2024 from 1200 to 1800hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024
Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024
Refer Market Notice 116996
AEMO no longer foresees a possible requirement for intervention to manage power system security in QLD region. The advice of possible intervention is cancelled from 2030 hrs 14/06/2024.
Manager NEM Real Time Operations
[EventId:202406141440_review] Prices for interval 14-Jun-2024 14:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Possible intervention to manage power system security in QLD Region
Possible intervention to manage power system security in QLD region
The synchronous generating units currently expected to be synchronised in North QLD from 2100 hrs 14/06/2024 will be inadequate to maintain a secure operating state in North QLD.
AEMO estimates that, in the absence of sufficient market response by 2030 hrs 14/06/2024, AEMO may need to intervene by issuing a direction requiring one or more North QLD synchronous generating unit(s) to operate or remain synchronised to maintain power system security in QLD.
Manager NEM Real Time Operations
[EventId:202406141435_review] Prices for interval 14-Jun-2024 14:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202406141430_review] Prices for interval 14-Jun-2024 14:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1425 hrs on 14 June 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 14-Jun-2024 14:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.