Filter by category
Filter by Date
Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Palmerston - Hadspen 3 & 4 110kV and
Cancellation time: 27/11/2024 10:19
Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 121030
Auto-generated on behalf of Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 121032
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1830 hrs 27/11/2024.
The direction update is issued at 1035 hrs 27/11/2024.
Manager NEM Real Time Operations
[EventId:202411271010_review] Prices for interval 27-Nov-2024 10:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1005 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 10:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411271005_review] Prices for interval 27-Nov-2024 10:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 10:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - NSW1 Region- 27/11/2024
Refer to AEMO Electricity Market Notice no. 121022.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
14:30 to 20:30 hrs 27/11/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.
Manager NEM Real Time Operations
[EventId:202411271000_review] Prices for interval 27-Nov-2024 10:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0955 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 10:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411270955_review] Prices for interval 27-Nov-2024 09:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0950 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 09:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411270950_review] Prices for interval 27-Nov-2024 09:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0945 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 09:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202411270945_review] Prices for interval 27-Nov-2024 09:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0940 hrs on 27 November 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 27-Nov-2024 09:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.