119105MARKET INTERVENTION20/10/2024 03:19:06 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 119104

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2100 hrs 21/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 20/10/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
119104MARKET INTERVENTION20/10/2024 01:11:29 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2100 hrs 21/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
119073MARKET INTERVENTION19/10/2024 03:34:48 PM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 119024

Direction is cancelled from: 1100 hrs 19/10/2024

Manager NEM Real Time Operations
119072MARKET INTERVENTION19/10/2024 04:34:15 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119025

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/10/2024.

The direction update is issued at 1630 hrs 19/10/2024.

Manager NEM Real Time Operations
119071MARKET INTERVENTION19/10/2024 04:32:59 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 119026

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 21/10/2024.

The direction update is issued at 1630 hrs 19/10/2024.

Manager NEM Real Time Operations
119055RESERVE NOTICE19/10/2024 11:10:41 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 19/10/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119023 is cancelled at 1100 hrs 19/10/2024.

Manager NEM Real Time Operations
119046RECLASSIFY CONTINGENCY19/10/2024 02:54:16 AM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 19/10/2024 02:54

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 119045

Auto-generated on behalf of Manager NEM Real Time Operations
119045RECLASSIFY CONTINGENCY19/10/2024 01:51:36 AM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 19/10/2024 01:51 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
119044RECLASSIFY CONTINGENCY18/10/2024 11:54:16 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 18/10/2024 23:54

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 119041

Auto-generated on behalf of Manager NEM Real Time Operations