122447MARKET INTERVENTION24/12/2024 11:31:06 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 122446

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 24/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1400 hrs 24/12/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
122446MARKET INTERVENTION24/12/2024 10:57:43 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2200 hrs 24/12/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
122444POWER SYSTEM EVENTS23/12/2024 08:40:02 PM

Update - Non-credible contingency event - SA region - 23/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - SA region - 23/12/2024

Refer AEMO Electricity Market Notice 122442

At 2036 hrs the Happy Valley - Morphett Vale East and the Morphett Vale - Cherry Gardens 275kV lines were returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
122442POWER SYSTEM EVENTS23/12/2024 04:44:55 PM

Non-credible contingency event - SA region - 23/12/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - SA region - 23/12/2024

At 1632 hrs the Happy Valley - Morphett Vale East 275kV Line and the Morphett Vale - Cherry Gardens 275kV line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
122441MARKET INTERVENTION23/12/2024 04:34:00 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122408

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 24/12/2024.

The direction update is issued at 1630 hrs 23/12/2024.

Manager NEM Real Time Operations
     
122440MARKET INTERVENTION23/12/2024 04:32:51 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122407

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 24/12/2024.

The direction update is issued at 1630 hrs 23/12/2024.

Manager NEM Real Time Operations
     
122437MINIMUM SYSTEM LOAD23/12/2024 02:38:20 PM

Forecast Minimum System Load (MSL1) condition in the VIC region on 29/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 29/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1760 MW
o MSL2 - 1260 MW
o MSL3 - 760 MW

The regional demand is forecast to be below the MSL1 threshold for the following period:

From 1000 hrs 29/12/2024 to 1400 hrs 29/12/2024. Minimum regional demand is forecast to be 1515 MW at 1230 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
122408MARKET INTERVENTION22/12/2024 04:01:37 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122373

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
122407MARKET INTERVENTION22/12/2024 04:00:18 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122372

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 24/12/2024.

The direction update is issued at 1600 hrs 22/12/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm