121468CONSTRAINTS09/12/2024 09:04:22 AM

Update to system strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 106175

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Clarke Creek wind farm in Far North Queensland, the system normal equations have been revised.



A revision to the constraint equations will be implemented at 1100 hrs on Monday 9th December 2024.

The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.

The constraint equation in the Q-NIL set of the form below will be modified:

-Q_NIL_STRGTH_KBWF
-Q_NIL_STRGTH_MEWF

Two new equations have been added:

-Q_NIL_STRGTH_CKWF
-Q_NIL_STRGTH_CKWF_I

AEMO Operations
     
121466NON-CONFORMANCE04/12/2024 09:05:45 PM

NON-CONFORMANCE Region VIC1 Wednesday, 4 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 4 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GANNB1
Duration: 04/12/2024 20:55 to 04/12/2024 21:05
Amount: -24 MW
Constraint: NC-V_GANNB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121444NON-CONFORMANCE04/12/2024 06:40:18 AM

NON-CONFORMANCE Region NSW1 Wednesday, 4 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 4 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 04/12/2024 06:25 to 04/12/2024 06:40
Amount: -16 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
121413NON-CONFORMANCE03/12/2024 11:15:53 AM

NON-CONFORMANCE Region NSW1 Tuesday, 3 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 3 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP6
Duration: 03/12/2024 11:05 to 03/12/2024 11:15
Amount: -58 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations
     
121409GENERAL NOTICE03/12/2024 10:22:45 AM

NEM Local Temperature Alerts for SA from 03 Dec 2024 to 07 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 5th Dec, 6th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
     
121357GENERAL NOTICE02/12/2024 10:41:14 AM

NEM Local Temperature Alerts for SA from 02 Dec 2024 to 06 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

SA
Port Augusta Ap (39+ Deg C): 5th Dec

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning


     
121312NON-CONFORMANCE01/12/2024 12:20:24 PM

NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GOONSF1
Duration: 01/12/2024 11:50 to 01/12/2024 12:20
Amount: 54 MW
Constraint: NC-N_GOONSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121310NON-CONFORMANCE01/12/2024 11:20:24 AM

NON-CONFORMANCE Region NSW1 Sunday, 1 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 1 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GOONSF1
Duration: 01/12/2024 09:55 to 01/12/2024 11:20
Amount: 35 MW
Constraint: NC-N_GOONSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
121169PRICE ADJUSTMENT28/11/2024 02:18:30 PM

[EventId:202411271510_confirmed] Prices for interval 27-Nov-2024 15:10 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1418 hrs on 28 November 2024

PRICES ARE NOW CONFIRMED for trading interval 27-Nov-2024 15:10.

In accordance with Market Notice 121092 AEMO has reviewed this trading interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
VIC1 -$30.00 -$29.50
RAISE60SEC
NSW1 $0.10 $0.05
QLD1 $0.10 $0.05
SA1 $0.10 $0.05
VIC1 $0.10 $0.05


This is an AEMO autogenerated Market Notice.
     