Market Notices

118373RESERVE NOTICE22/09/2024 04:15:36 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118363 is cancelled at 16:15 hrs 22/09/2024.

Manager NEM Real Time Operations
118363RESERVE NOTICE22/09/2024 12:54:20 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

[1.] From 1830 hrs 23/09/2024 to 2030 hrs 23/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 260 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118362RESERVE NOTICE22/09/2024 03:02:38 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118361 is cancelled at 0300 hrs 22/09/2024.

No LOR2 condition is currently forecast in the STPASA period.

Manager NEM Real Time Operations
118361RESERVE NOTICE21/09/2024 10:35:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

[1.] From 1430 hrs 24/09/2024 to 1600 hrs 24/09/2024.
The forecast capacity reserve requirement is 516 MW.
The minimum capacity reserve available is 462 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
118342GENERAL NOTICE20/09/2024 04:43:35 PM

Update - Lightning vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region

Refer to AEMO Electricity Market Notice 118320 ,118321, 118322

At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.

In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.

Manager NEM Real Time Operations
118322POWER SYSTEM EVENTS19/09/2024 04:16:27 PM

Update - Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 19/09/2024

Refer AEMO Electricity Market Notice 118321

At 1446 hrs the Gordon - Chapel St No 1 and No 2 220 kV lines were returned to service.

This non-credible contingency event was caused by lightning. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.


Manager NEM Real Time Operations
118321POWER SYSTEM EVENTS19/09/2024 03:28:41 PM

Update - Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - TAS region - 19/09/2024

At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has advised of approximately 112 MW disconnection of bulk electrical load,
disconnection of generation at Studland Bay Wind generator (71 MW) and 23 MW generation reduction at Gordon Power station.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
118320POWER SYSTEM EVENTS19/09/2024 01:54:59 PM

Non-credible contingency event - TAS region - 19/09/2024

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - TAS region - 19/09/2024

At 1340 hrs the Gordon - Chapel St No1 and No 2 220 kV lines tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
118319GENERAL NOTICE19/09/2024 01:45:31 PM

Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.

A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.

During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm