Market Notices

121791RESERVE NOTICE12/12/2024 03:45:39 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121719 has been updated at 1400 hrs 12/12/2024 to the following:

1. From 1230 hrs to 1430 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 825 MW.

2. From 2030 hrs to 2200 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

AEMO Operations
     
121782RESERVE NOTICE12/12/2024 01:09:03 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 1630 hrs 13/12/2024 to 1830 hrs 13/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 881 MW.

[2.] From 1900 hrs 13/12/2024 to 1930 hrs 13/12/2024.
The forecast capacity reserve requirement is 1459 MW.
The minimum capacity reserve available is 1362 MW.


Manager NEM Real Time Operations
     
121766MARKET INTERVENTION12/12/2024 09:31:31 AM

Cancellation - AEMO Intervention Event - SA region 11/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/12/2024

Refer to Market Notice 121721

The AEMO Intervention Event and all associated directions are cancelled from 0930 hrs on 12/12/2024.


Manager NEM Real Time Operations
     
121763MARKET INTERVENTION12/12/2024 09:30:08 AM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121722

Direction is cancelled from: 0930 hrs 12/12/2024

Manager NEM Real Time Operations
     
121761RESERVE NOTICE12/12/2024 08:51:13 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 12/12/2024 to 1930 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1075 MW.


Manager NEM Real Time Operations
     
121756RESERVE NOTICE12/12/2024 07:50:25 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1283 MW.


Manager NEM Real Time Operations
     
121755NON-CONFORMANCE12/12/2024 05:40:16 AM

NON-CONFORMANCE Region NSW1 Thursday, 12 December 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 12 December 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW02
Duration: 12/12/2024 05:35 to 12/12/2024 05:40
Amount: -31 MW
Constraint: NC-N_BW02

Auto-generated on behalf of Manager NEM Real Time Operations
     
121752RESERVE NOTICE12/12/2024 04:25:47 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1830 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1401 MW.


Manager NEM Real Time Operations
     
121722MARKET INTERVENTION11/12/2024 04:07:36 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 121721


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 11/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0830 hrs 12/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0930 hrs 12/12/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm