Market Notices

122340MARKET INTERVENTION21/12/2024 03:54:16 AM

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 122297

Direction is cancelled from: 0400 hrs 21/12/2024

Manager NEM Real Time Operations
     
122326MARKET SYSTEMS20/12/2024 04:16:29 PM

INC0139532 | Impact to Prudentials

AEMO ELECTRICITY MARKET NOTICE

SERVICE INTERRUPTION - ALERT

The service interruption relating to Prudentials & Settlements have now been resolved.
AEMO is working on the issue and will provide updates as more information becomes available.

For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
     
122312MARKET INTERVENTION20/12/2024 02:45:17 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 122279


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1445 hrs 20/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0400 hrs 21/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 22/12/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
122311MARKET INTERVENTION20/12/2024 02:43:35 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 122277

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 22/12/2024.

The direction update is issued at 1445 hrs 20/12/2024.

Manager NEM Real Time Operations
     
122308MINIMUM SYSTEM LOAD20/12/2024 12:58:35 PM

Cancellation of Forecast Minimum System Load MSL2 event in the VIC Region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast MSL2 - VIC Region at 1200 hrs 20/12/2024.

Refer to Market Notice 122305 for MSL2.

AEMO Operations
     
122305MINIMUM SYSTEM LOAD20/12/2024 08:53:36 AM

Forecast Minimum System Load (MSL2) condition in the VIC region on 22/12/2024

AEMO ELECTRICITY MARKET NOTICE
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 22/12/2024.

Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1825 MW
o MSL2 - 1325 MW
o MSL3 - 825 MW

The regional demand is forecast to be below the MSL2 threshold for the following period:

From 1230 hrs 22/12/2024 to 1300 hrs 22/12/2024. Minimum regional demand is forecast to be 1284 MW at 1300 hrs.

Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .

AEMO Operations
     
122297MARKET INTERVENTION20/12/2024 07:30:11 AM

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 122283

The MINTARO MINTARO GAS direction is now expected to start at 0830 hrs 20/12/2024.

The direction update is issued at 0725 hrs 20/12/2024.

Manager NEM Real Time Operations
     
122289MINIMUM SYSTEM LOAD19/12/2024 08:28:50 PM

Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Forecast Minimum System Load (MSL) MSL2 event in the VIC Region on 22/12/2024.

Cancellation - Forecast MSL2- VIC Region at 2030 hrs 22/12/2024.

Refer to Market Notice 122275for MSL2.

Manager NEM Real Time Operations
     
122283MARKET INTERVENTION19/12/2024 04:55:10 PM

Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Synergen Power Pty Limited - MINTARO MINTARO GAS

Refer to Market Notice 122276


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Synergen Power Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS at 1700 hrs 19/12/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 20/12/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 21/12/2024.

Synergen Power Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm