Filter by category
Filter by Date
Request for Generator Recall Information for the period 16/12/2024 for Region VIC
Refer to AEMO Electricity Market Notice no. 121767.
Please provide Generator Recall Information for the period 16/12/2024, by 1200 hrs on 13/12/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.
SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf
Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1283 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1830 hrs 12/12/2024 to 1900 hrs 12/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1401 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/12/2024
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 1530 hrs 16/12/2024 to 1600 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 10 MW at 1530 hrs.
[2.] From 1700 hrs 16/12/2024 to 1830 hrs 16/12/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 106 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121693 is cancelled at 1400 hrs 11/12/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/12/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121692 has been updated at 1400 hrs 11/12/2024 to the following:
1. From 1500 hrs to 1700 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
2. From 1900 hrs to 2030 hrs 16/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 13/12/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
1. From 1630 hrs to 1900 hrs 13/12/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1336 MW.
AEMO Operations
CHG0100201 | Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 16/12/2024 08:12:00 AEST
Outage 1 End Date & Time: 16/12/2024 08:13:00 AEST
Outage 2 Start Date & Time: 16/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 16/12/2024 15:13:00 AEST
Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 08:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.
During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.
Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0100220 | Completed | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Electricity Market Management System_PreProd
Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.