Market Notices

118489GENERAL NOTICE27/09/2024 09:51:41 PM

Network Augmentation Commissioned - NSW Region - 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

A network augmentation has been commissioned in the NSW region at 2150 hrs 27/09/2024 as follows:

Walla Walla substation has been cut into the existing Wagga - Jinderra (62) 330 kV line to form the following circuits:

Jinderra - Walla Walla 62 330 kV Transmission Line
Walla Walla - Wagga 6Y 330 kV Transmission Line

Manager NEM Real Time Operations
118483MINIMUM SYSTEM LOAD27/09/2024 03:35:11 PM

Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.

AEMO ELECTRICITY MARKET NOTICE
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Refer to Market Notice 118442 for MSL1.
Manager NEM Real Time Operations
118475MINIMUM SYSTEM LOAD27/09/2024 10:55:57 AM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 118421.

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.

Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
118442MINIMUM SYSTEM LOAD25/09/2024 03:14:36 PM

Minimum System Load 1 (MSL1) in the VIC Region on 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1300 hrs 27/09/2024 to 1330 hrs 27/09/2024.

Minimum regional demand is forecast to be 1879 MW at 1330 hrs, and the advisory threshold is:
o MSL1 - 1915 MW
o MSL2 - 1415 MW
o MSL3 - 915 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
118427GENERAL NOTICE24/09/2024 03:38:49 PM

Network Augmentation Commissioned - NSW Region - 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 24/09/2024

At 1535 hrs Buronga - Redcliffs X1 220 kV line has been commissioned.


Manager NEM Real Time Operations
118421MINIMUM SYSTEM LOAD24/09/2024 02:54:54 PM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
118342GENERAL NOTICE20/09/2024 04:43:35 PM

Update - Lightning vulnerable lines in TAS region

AEMO ELECTRICITY MARKET NOTICE.

Update - Lightning vulnerable lines in TAS region

Refer to AEMO Electricity Market Notice 118320 ,118321, 118322

At 1340 hrs 19/09/2024 the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line tripped.
The cause of the trip was identified as due to Lightning.

In accordance with SO_OP_3715, AEMO now considers the Gordon - Chapel St No 1 220 kV line and the Gordon - Chapel St No 2 220 kV line to be vulnerable with a category of Vulnerability due to Lightning.

Manager NEM Real Time Operations
118319GENERAL NOTICE19/09/2024 01:45:31 PM

Planned outage of Tailem Bend - South East 275 kV transmission line in the South Australia region beginning on 20/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Tailem Bend - South East No 1 275 kV line in the South Australian (SA) region is planned to be out of service from 2100 hrs on 20/09/2024 to 0530 hrs on 21/09/2024.

A credible contingency event during this planned outage could cause synchronous separation of the SA region from the rest of the NEM.

During this planned outage:
- Power transfer will be restricted across the VIC - SA interconnector (Heywood interconnector); and
- Post contingent FCAS will be sourced within SA following Separation event.

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO Operations
118257SETTLEMENTS RESIDUE12/09/2024 04:55:27 PM

[EventId:202409121655_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 12 September 2024 16:55

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1655 hrs on 12 September 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 12 September 2024.

Refer to market notice: 118256

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1655 hrs on 12 September 2024.

This is an AEMO autogenerated Market Notice.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm