117492RESERVE NOTICE27/07/2024 02:39:39 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117468 has been updated at 1400 hrs 27/07/2024 to the following:

From 0730 hrs 30/07/2024 to 0930 hrs 30/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 501 MW.

AEMO Operations
117491RESERVE NOTICE27/07/2024 02:38:27 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117467 has been updated at 1400 hrs 27/07/2024 to the following:

[1.] From 0700 hrs 29/07/2024 to 0930 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 470 MW.

[2.] From 1730 hrs 29/07/2024 to 1930 hrs 29/07/2024.
The forecast capacity reserve requirement is 557 MW.
The minimum capacity reserve available is 534 MW.

AEMO Operations
117468RESERVE NOTICE26/07/2024 03:02:08 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0730 hrs to 0900 hrs 30/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 537 MW.

AEMO Operations
117467RESERVE NOTICE26/07/2024 03:15:15 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117442 has been updated at 1400 hrs 26/07/2024 to the following:

From 0700 hrs to 0930 hrs 29/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 461 MW.

AEMO Operations
117466GENERAL NOTICE30/07/2024 09:20:28 PM

Network Augmentation Commissioned - VIC Region - 30/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 30/07/2024

Cressy Terminal Station has been cut into the existing Moorabool - Mortlake No.2 500 kV line to form the following circuits:

Cressy - Mortlake No.2 500 kV line
Cressy - Moorabool No.2 500 kV line

Manager NEM Real Time Operations
117443RESERVE NOTICE25/07/2024 03:08:03 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 31/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0800 hrs to 0900 hrs 31/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.

AEMO Operations
117442RESERVE NOTICE25/07/2024 03:06:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 29/07/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0730 hrs to 0900 hrs 29/07/2024.
The forecast capacity reserve requirement is 555 MW.
The minimum capacity reserve available is 524 MW.

AEMO Operations
117356GENERAL NOTICE18/07/2024 09:06:38 PM

Network Augmentation Commissioned - VIC Region - 18/07/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - VIC Region - 18/07/2024

At 2044 hrs 18,07/2024, Cressy Terminal Station has been cut into the existing Moorabool - Haunted Gully No.1 500 kV line to form the following circuits:

Cressy - Haunted Gully No 1 500 kV line
Cressy - Moorabool No 1 500 kV line

Manager NEM Real Time Operations
117321LOAD SHED08/07/2024 07:08:46 PM

Load Shedding Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the NSW Region

AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region

to maintain power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations