CHG0091339 | Completed | Production | NSW Marketnet Router Replacement
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Market Network
Change Title: NSW Marketnet Router Replacement
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Network Augmentation Commissioned - NSW Region - 01/09/2024
Network Augmentation Commissioned - NSW Region - 01/09/2024
At 2125 hrs. Buronga -Redcliffs X9 220 kV line has been commissioned.
At 2125 hrs. Buronga -Redcliffs OX1 220 kV line has been de-commissioned.
Manager NEM Real Time Operations
[EventId:202408291910_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 August 2024 19:10
Issued by Australian Energy Market Operator Ltd at 1910 hrs on 29 August 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 August 2024.
Refer to market notice: 117960
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1910 hrs on 29 August 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202408291805_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 August 2024 18:05
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 29 August 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 August 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1805 hrs on 29 August 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202408291330_NRM_QLD1_NSW1_stopped] NEGRES CONSTRAINT NRM_QLD1_NSW1 ceased operating from 29 August 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 29 August 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 August 2024.
Refer to market notice: 117941
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the QLD to NSW directional interconnector.
The negative residue constraint NRM_QLD1_NSW1 ceased operating at 1330 hrs on 29 August 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202408291235_NRM_QLD1_NSW1_started] NEGRES CONSTRAINT NRM_QLD1_NSW1 started operating from 29 August 2024 12:35
Issued by Australian Energy Market Operator Ltd at 1235 hrs on 29 August 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - QLD to NSW - 29 August 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the QLD to NSW directional interconnector.
The negative residue constraint set NRM_QLD1_NSW1 commenced operating from 1235 hrs on 29 August 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
N-Q-MNSP1
NSW1-QLD1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0089859 | Completed | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas FRC - CATS
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
QNI Minor testing (NSW to Qld) 28th August 2024
Refer to market notice 117650
There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 850 MW on Wednesday 28th August 2024 from 1300 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
[EventId:202408271910_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 27 August 2024 19:10
Issued by Australian Energy Market Operator Ltd at 1910 hrs on 27 August 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 27 August 2024.
Refer to market notice: 117905
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1910 hrs on 27 August 2024.
This is an AEMO autogenerated Market Notice.