STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region beginning on 02/07/2024
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 117249 has been updated at 1420 hrs 30/06/2024 to the following:
[1.] From 0800 hrs 02/07/2024 to 0830 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 644 MW.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region beginning on 02/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following periods:
[1.] From 0800 hrs 02/07/2024 to 0830 hrs 02/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 637 MW.
[2.] From 0800 hrs 03/07/2024 to 0830 hrs 03/07/2024.
The forecast capacity reserve requirement is 646 MW.
The minimum capacity reserve available is 637 MW.
Manager NEM Real Time Operations
Fast Frequency Response Market - Dispatch of R1 and L1 FCAS in the SA region during island conditions from 1 July 2024
From 1 July 2024 AEMO will dispatch R1 and L1 FCAS locally in the SA region during conditions of actual islanding of the SA region.
This follows the end of contracts for Fast Frequency Response (FFR) in the SA region.
The dispatch of R1 and L1 FCAS under these island conditions will not be capped.
These changes are only applicable for conditions of actual SA islanding from the rest of the NEM.
No other changes to the dispatch of R1 and L1 FCAS will be made on this date.
For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response
Andrew Groom
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2023
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117203 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117202 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117201 is cancelled at 1400 hrs 27/06/2024.
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
Non-credible contingency event - NSW region - 27/06/2024
Non-credible contingency event - NSW region - 27/06/2024
At 0845 hrs the Sydney West No.1 330 kV SVC tripped during switching for planned outage of Sydney West No.4 330/132 kV transformer.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 03/07/2024.
The forecast capacity reserve requirement is 532 MW.
The minimum capacity reserve available is 505 MW.
2. From 1730 hrs to 2030 hrs 03/07/2024.
The forecast capacity reserve requirement is 526 MW.
The minimum capacity reserve available is 496 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0800 hrs to 0900 hrs 02/07/2024.
The forecast capacity reserve requirement is 536 MW.
The minimum capacity reserve available is 454 MW.
2. From 1730 hrs to 2130 hrs 02/07/2024.
The forecast capacity reserve requirement is 546 MW.
The minimum capacity reserve available is 414 MW.