Filter by category
Filter by Date
[EventId:202407251115_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 25 July 2024 11:15
Issued by Australian Energy Market Operator Ltd at 1115 hrs on 25 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.
Refer to market notice: 117439
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1115 hrs on 25 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407251000_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 25 July 2024 10:00
Issued by Australian Energy Market Operator Ltd at 1000 hrs on 25 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1000 hrs on 25 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202407201430_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 20 July 2024 14:30
Issued by Australian Energy Market Operator Ltd at 1430 hrs on 20 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.
Refer to market notice: 117382
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1430 hrs on 20 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407201330_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 20 July 2024 13:30
Issued by Australian Energy Market Operator Ltd at 1330 hrs on 20 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 20 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1330 hrs on 20 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024
Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024
Refer to AEMO Electricity Market Notice 117322
Load restoration as directed is complete. Direction cancelled from 2200 hrs 08/07/2024
Manager NEM Real Time Operations
Load Restoration Direction in the NSW Region
Load Restoration Direction in the NSW Region
AEMO has directed load restoration commencing at 1930 hrs 08/07/2024
in the NSW region
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
[EventId:202407031755_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 03 July 2024 17:55
Issued by Australian Energy Market Operator Ltd at 1755 hrs on 3 July 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.
Refer to market notice: 117283
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1755 hrs on 3 July 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202407031730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 03 July 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 3 July 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 3 July 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 3 July 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/06/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 117049 is cancelled at 1600 hrs 18/06/2024.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations