Filter by category
Filter by Date
Foreseeable AEMO intervention in SA region
Foreseeable AEMO intervention in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 07/12/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1615 hrs 06/12/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Forecast Minimum System Load (MSL1) condition in the VIC region on 08/12/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 08/12/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1590 MW
o MSL2 - 1090 MW
o MSL3 - 590 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1200 hrs 08/12/2024 to 1330 hrs 08/12/2024. Minimum regional demand is forecast to be 1496 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Update to system strength requirements in North Queensland
Refer to market notice 106175
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Clarke Creek wind farm in Far North Queensland, the system normal equations have been revised.
A revision to the constraint equations will be implemented at 1100 hrs on Monday 9th December 2024.
The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases. Additional information has been included in the limit advice to clarify the requirement to disconnect all inverters/turbines under certain system conditions.
The constraint equation in the Q-NIL set of the form below will be modified:
-Q_NIL_STRGTH_KBWF
-Q_NIL_STRGTH_MEWF
Two new equations have been added:
-Q_NIL_STRGTH_CKWF
-Q_NIL_STRGTH_CKWF_I
AEMO Operations
STPASA - Update of the suspect Lack Of Reserve Level 3 (LOR3) condition in the NSW Region on 06/12/2024
The suspect LOR3 condition advised in AEMO Electricity Market Notice No. 121292 has been reviewed.
AEMO considers this forecast LOR3 condition invalid. Subsequent STPASA runs are producing valid solutions.
AEMO Operations
STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the NSW Region on 06/12/2024
AEMO considers that there is a suspect Forecast LOR3 condition for the NSW region for the following period:
From 1630 hrs 06/12/2024 to 1700 hrs 06/12/2024.
AEMO is currently investigating this LOR3 forecast condition to confirm whether they are valid.
AEMO Operations
Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024
Cancellation - Foreseeable intervention to manage power system security in SA region 30/11/2024
Refer Market Notice 121281
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 0915 hrs 30/11/2024.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 121280
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 0900 hrs 30/11/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1100 hrs 30/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Cancellation - AEMO Intervention Event - SA region 27/11/2024
Refer to Market Notice 121094
The AEMO Intervention Event and all associated directions are cancelled from 1500 hrs on 28/11/2024.
Manager NEM Real Time Operations