121526RESERVE NOTICE06/12/2024 03:53:51 PM

Cancellation of Actual (LOR1) condition in the NSW region - 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 06/12/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.121520 is cancelled at 1550 hrs 06/12/2024.

Manager NEM Real Time Operations
     
121520RESERVE NOTICE06/12/2024 02:57:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 06/12/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1430 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1350 MW.
The minimum capacity reserve available is 1248 MW.


Manager NEM Real Time Operations
     
121504RESERVE NOTICE06/12/2024 01:25:11 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 06/12/2024 to 1830 hrs 06/12/2024.
The forecast capacity reserve requirement is 1724 MW.
The minimum capacity reserve available is 1675 MW.

Manager NEM Real Time Operations
     
121438RESERVE NOTICE03/12/2024 05:30:53 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1800 hrs 03/12/2024 to 1830 hrs 03/12/2024.
The forecast capacity reserve requirement is 1573 MW.
The minimum capacity reserve available is 1541 MW.

Manager NEM Real Time Operations
     
121424RESERVE NOTICE03/12/2024 02:30:08 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121414 is cancelled at 1415 hrs 03/12/2024.

Manager NEM Real Time Operations
     
121416RESERVE NOTICE03/12/2024 12:44:49 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 03/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 121406 is cancelled at 1215 hrs 03/12/2024.

Manager NEM Real Time Operations
     
121414RESERVE NOTICE03/12/2024 11:24:50 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121405 has been updated at 1115 hrs to the following:

[1.] From 1330 hrs 03/12/2024 to 1600 hrs 03/12/2024.
The forecast capacity reserve requirement is 1367 MW.
The minimum capacity reserve available is 1081 MW.

Manager NEM Real Time Operations
     
121406RESERVE NOTICE03/12/2024 08:09:47 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the Qld Region on 03 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 121386 has been updated at 0750 hrs to the following:

[1.] From 1800 hrs 03/12/2024 to 1930 hrs 03/12/2024.
The forecast capacity reserve requirement is 1127 MW.
The minimum capacity reserve available is 991 MW.

Manager NEM Real Time Operations
     
121405RESERVE NOTICE03/12/2024 07:58:55 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 03 Dec 2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121392 has been updated at 0750hrs to the following:

[1.] From 1200 hrs 03/12/2024 to 1400 hrs 03/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1129 MW.

[2.] From 1430 hrs 03/12/2024 to 1500 hrs 03/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1326 MW.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm