Market Notices

121716MARKET SYSTEMS11/12/2024 02:53:46 PM

CHG0100201 | Planned maintenance affecting the AEMO Market Network ***Outage Updated***

Change Number: CHG0100201
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MarketNet
Change Title: Planned maintenance affecting the AEMO Market Network ***Outage Updated***
Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage 1 Start Date & Time: 16/12/2024 08:12:00 AEST
Outage 1 End Date & Time: 16/12/2024 08:13:00 AEST
Outage 2 Start Date & Time: 16/12/2024 15:12:00 AEST
Outage 2 End Date & Time: 16/12/2024 15:13:00 AEST

Environment: Production
Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 08:00AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During the change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
121710MARKET SYSTEMS11/12/2024 08:34:18 AM

CHG0100220 | Completed | Pre-Production | Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Change Number: CHG0100220

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: Electricity Market Management System_PreProd

Change Title: Pre-Production Electricity Market Management System (EMMS) Maintenance - Outages

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
121704RESERVE NOTICE10/12/2024 06:42:57 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 10/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121702 is cancelled at 1840 hrs 10/12/2024.

Manager NEM Real Time Operations
     
121702RESERVE NOTICE10/12/2024 06:13:20 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1830 hrs 10/12/2024 to 1900 hrs 10/12/2024.
The forecast capacity reserve requirement is 1320 MW.
The minimum capacity reserve available is 1197 MW.

Manager NEM Real Time Operations
     
121701RESERVE NOTICE10/12/2024 05:55:32 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 10/12/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 121698 is cancelled at 1745 hrs 10/12/2024.

Manager NEM Real Time Operations
     
121698RESERVE NOTICE10/12/2024 04:26:39 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1830 hrs 10/12/2024 to 1900 hrs 10/12/2024.
The forecast capacity reserve requirement is 1385 MW.
The minimum capacity reserve available is 1336 MW.

Manager NEM Real Time Operations
     
121696MARKET SYSTEMS10/12/2024 04:15:03 PM

CHG0100201 | Production | Planned maintenance affecting the AEMO Market Network

Change Number: CHG0100201

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MarketNet

Change Title: Planned maintenance affecting the AEMO Market Network.

Change Start Date & Time: 16/12/2024 08:00:00 AEST
Change End Date & Time: 17/12/2024 17:00:00 AEST
Outage Start Date & Time: 16/12/2024 15:12:00 AEST
Outage End Date & Time: 16/12/2024 15:13:00 AEST

Environment: Production

Participant Impact and Requirements: Planned maintenance will be conducted on the 16th of December 2024, between 07:30AM and 05:00PM AEST on the core network infrastructure within the AEMO Market Network in Brisbane.

During there change, there will be two instances of 1-3 second service disruption to MarketNet Services accessed via Brisbane as traffic moves from the active to the standby load balancing unit. All Services should return to normal after this time. Traffic via Sydney will not be affected during this time. AEMO recommends that all market participants with site to site VPN connections currently connected via Brisbane, to switch these connections to the Sydney site as a precaution.

Participants connecting via IPWAN and/or SSL VPN will be automatically connected to the Sydney site and do not need to take any action.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
121695INTER-REGIONAL TRANSFER10/12/2024 03:31:22 PM

Update - Inter-regional transfer limit variation - constraint automation to manage Power System Security in QLD region - 10 Dec 2024

AEMO ELECTRICITY MARKET NOTICE
Refer to MN 121688
In order to maintain the power system in a secure operating state in the QLD region, AEMO has invoked automated constraint set CA_SYD_566A36E5 from 1245 hrs to 1510 hrs.

This constraint set contains equations with the following interconnector on the LHS;

NSW1-QLD1, N-Q_MNSP1

Refer to AEMO Network Outage Scheduler (NOS) for further information.

Manager NEM Real Time Operations
     
121693RESERVE NOTICE10/12/2024 03:08:44 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 17/12/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

1. From 1700 hrs to 1830 hrs 17/12/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1310 MW.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm