Market Notices

118493MINIMUM SYSTEM LOAD28/09/2024 02:30:26 PM

Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - MSL1- VIC Region at 1430 hrs 28/09/2024.
Refer to Market Notice 118475.

Manager NEM Real Time Operations
118483MINIMUM SYSTEM LOAD27/09/2024 03:35:11 PM

Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.

AEMO ELECTRICITY MARKET NOTICE
Cancellation - MSL1- VIC Region at 1530 hrs 27/09/2024.
Refer to Market Notice 118442 for MSL1.
Manager NEM Real Time Operations
118475MINIMUM SYSTEM LOAD27/09/2024 10:55:57 AM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

Update to Market Notice 118421.

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1030 hrs to 1430 hrs 28/09/2024.

Minimum regional demand is forecast to be 1420 MW at 1200 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
118442MINIMUM SYSTEM LOAD25/09/2024 03:14:36 PM

Minimum System Load 1 (MSL1) in the VIC Region on 27/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1300 hrs 27/09/2024 to 1330 hrs 27/09/2024.

Minimum regional demand is forecast to be 1879 MW at 1330 hrs, and the advisory threshold is:
o MSL1 - 1915 MW
o MSL2 - 1415 MW
o MSL3 - 915 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in action such as the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
118421MINIMUM SYSTEM LOAD24/09/2024 02:54:54 PM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
118323CONSTRAINTS19/09/2024 04:20:22 PM

Update to system normal constraint equation in NSW for transient voltage stability in south-west NSW

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 92840.

Transgrid has advised AEMO of an update to the transient voltage stability limit in south-west NSW for loss of Darlington Point to Wagga (63) 330 kV line. The limit will include terms for the Darlington Point and Riverina BESS.

The following constraint equation will be updated with the above changes at 1100 hrs Friday 20th September 2024.
N::N_NIL_63

For full details on the formulation, the new constraint equation has now been loaded into AEMO's pre-production systems.

For further details on these constraint equation please contact ben.blake@aemo.com.au

Ben Blake
AEMO Operations
117324LOAD RESTORE08/07/2024 09:58:40 PM

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Load Restoration Direction in the NSW Region - 08/07/2024

Refer to AEMO Electricity Market Notice 117322
Load restoration as directed is complete. Direction cancelled from 2200 hrs 08/07/2024

Manager NEM Real Time Operations
117322LOAD RESTORE08/07/2024 07:34:37 PM

Load Restoration Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Restoration Direction in the NSW Region

AEMO has directed load restoration commencing at 1930 hrs 08/07/2024
in the NSW region

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
117321LOAD SHED08/07/2024 07:08:46 PM

Load Shedding Direction in the NSW Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the NSW Region

AEMO has directed load shedding commencing at 1817 hrs 08/07/2024
in the NSW region

to maintain power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm